Friday 15 May 2015

Week 17

This week the 1st floor polystyrene was installed, ducting for heating and cooling installed, temporary doors installed and the first coat of render was put on.  

The cavity sliders (rail) have been installed to the ensuite bathrooms and the bath niches have also been constructed.

We also had a meeting with our site supervisor who informed us that everything is going smoothly and that we should be at 'lock up' in the next two weeks.

The weather looks like it will turn to the better next week, so we should see the eaves finished, the 2nd coat of render completed, the remaining windows installed and the scaffolding removed.  

Here are some pics!

Extra polystyrene:


Ducting in ceiling ground floor:



Hallway looking towards front door, door to garage on the left


Main Bathroom:


Minor Ensuite 1:


Master Bath:


Polystyrene on the upstairs balcony:




First Coat of Render: